I am looking for information relating to a series of tests which could be performed after some new SAN Fabric switches have been installed in order to show that they are working . . . my customer is asking for some basic tests which could be performed, and rather than reinvent the wheel, I was wondering whether anyody had anyhting which they could share.

 

Has anyody got any previously used test plans?


Sean

Frequent Contributor
Posts: 80
Registered: ‎01-28-2010

Re: SAN Fabric Testing

the question is, what do you want to test

or better what does the customer want to get answered with a test!

 

and no i have not used test plans, SAN works or it does not work that simple it is :)

 

but, there are some basic tests you can run when implementing ISL.

first you can use the D port config to run diag test on ISL ports connected to each other.

 

or the more demanding test that can be run in a life enviroment, but with caution

with the command spinfab you can test if the ISL are working correct

*spinFab  -  Runs  functional  test of interswitch link (ISL)
     cabling and trunk group operation.

 

i would use this command only if the fabrics arent in production yet.

 

never the less ask your customer what answers he is looking for

 

 